Construction Phase

Construction Announcements

Erection of Structural Steel commenced in December 2025!

Erection of Structural Steel commenced in December 2025 and scheduled to complete in April 2026! Please check back periodically for any future updates. Click on the link below to view Consigli’s steel erection logistics/crane location plan.

Steel Erection Logistic Plan – Crane Locations

Increased Rodent activity around new Pickering Construction Site?

Construction activities can disturb rodents living in/below/around construction sites. Experiencing increased rodent activity around you house, please fill out the form using the link below. The City will install bait boxes on your property. Please send the filled out form to isdonline@lynnma.gov. You can contact the Lynn Inspectional Services office at (781) 598-4000 with any questions.

https://www.lynnma.gov/cms/one.aspx?portalId=109810&pageId=136766

Construction Working Hours

Monday through Friday: 7 a.m. to 6 p.m.
(Saturday and Sunday work require local authorization)

Construction Progress Photos

(click on the photos to enlarge with descriptions)

Week of February 20, 2026

Structural steel erection progress as of February 20, 2026 (facing north).
Structural steel erection progress as of February 20, 2026 (facing west) with Tarping for "Winter Condition/Temporary Heating" extended to the second floor.
Delivery of rebar for future concrete floor slab placement.

Week of February 13, 2026

Installation of Tarping for "Winter Condition/Temporary Heating" to support concrete work.
Electrical room box-outs for duct bank penetrations.
Installation of underground electrical ductbanks and final connections for building penetrations.

Week of February 06, 2026

Structural steel erection progress as of February 06, 2026 (facing southeast).
Structural steel erection progress as of February 06, 2026 (facing north).
Delivery of temporary/portable heaters in preparation for rebar/concrete placement.

Week of January 30, 2026

Installation of underground service lines for future site lighting.
Installation of stair stingers and pans.
Structural steel erection progress as of January 30, 2026 (facing west).
Structural steel erection progress as of January 30, 2026 (facing north).

Week of January 23, 2026

Structural steel erection progress as of January 23, 2026 (facing north).
Structural steel erection progress as of January 23, 2026 (facing north).
Installation of underground electrical conduit banks is ongoing.

Week of January 16, 2026

Structural steel erection progress as of January 16, 2026 (facing north).
Installation of Retaining Wall is nearing completion.
Structural steel erection progress as of January 16, 2026 (facing west).
Installation of underground electrical conduit banks.
Installation of steel decking (1st Floor).

January 2026 Drone Photos

Week of January 09, 2026

Transporting remaining soil stockpiles off-site is nearing completion.
Structural steel erection progress as of January 09, 2026 (near future front entrance).
Delivery of structural steel is ongoing.
Structural steel erection progress as of January 09, 2026 (facing southeast).
Structural steel erection progress as of January 09, 2026 (facing north).
Structural steel erection progress as of January 09, 2026 (facing south).

Week of January 02, 2026

Applying waterproofing to concrete foundation wall.
Structural steel erection is ongoing.
Structural steel erection progress (cont.)

Week of December 26, 2025

Crane assembly for structural steel erection.
Structural steel deliveries commenced.
Structural steel erection commenced.

Week of December 19, 2025

Crane delivery for steel erection.
Backfilling of structural fill.
Asphalt Binder placement in preparation for steel deliveries.

December 2025 Drone Photos

Week of December 12, 2025

Excavating for underground utilities and building foundation.
Installation of permanent stainless steel guardrails/handrails for Sission student playgroud access ramp is nearing completion.
Concrete pour for tall foundation walls.
Applying waterproofing to concrete foundation wall.
Grading crushed stone in preparation for asphalt binder placement.

Week of December 05, 2025

Concrete forms placed for the building foundation.
Exterior Masonry (Brick) Mockup.
Current progress of concrete foundations for new Pickering Middle School.
Installation of permanent stainless steel guardrails/handrails commenced for Sission student playgroud access ramp

Week of November 28, 2025

Laying gravel in preparation for asphalt binder placement for the future main parking lot, which will be utilized for structural steel deliveries.
Installation of concrete forms in preparation for concrete foundation pour is ongoing.
Delivery/Installation of a centralized, exterior grease trap.

Week of November 21, 2025

Transporting remaining soil stockpiles off-site is ongoing.
Delivery of a heater and fuel cell delivered to the site in preparation for pouring concrete (foundations) in cold temperatures.
Installation of temporary power conduit.
Installation of rebar for the northwest continuous footing is ongoing.

Week of November 14, 2025

Installation of foundation AVB (Self-Adhered Air and Vapor Barrier Membrane) is ongoing.
Steel Rebar delivered to site for foundations.
Placement of steel rebar in preparation for foundation concrete pour.

Week of November 07, 2025

Loading excavated soil stockpiles for transportation off-site.
Installation of forms and rebar for foundation footing concrete pour.
Installation of AVB (Self-Adhered Air and Vapor Barrier Membrane).
Forms removed from new foundation walls.

Construction Logistics Plan

COMPLETED PHASES                        

Trucking/Delivery Route
Crane Locations for steel erection.
Loading Bay Zones

CURRENT PHASE                                

Early Structure - Janaury 2026

UPCOMING PHASES                                

Structure/Early Facade - Summer 2026
Project Complete - December 2027
Building Facade - Summer 2026 - January 2027
Hardscape - Summer 2027

COMPLETED PHASES

Early Enabling - Spring 2024
Enabling/Demo - Summer 2024
Foundations - Summer 2025 - December 2025