Construction Phase

Construction Announcements

Erection of Structural Steel commened in December 2025!

Erection of Structural Steel commenced in December 2025 and scheduled to complete in April 2026! Please check back periodically for any future updates. Click on the link below to view Consigli’s steel erection logistics/crane location plan.

Steel Erection Logistic Plan – Crane Locations

Increased Rodent activity around new Pickering Construction Site?

Construction activities can disturb rodents living in/below/around construction sites. Experiencing increased rodent activity around you house, please fill out the form using the link below. The City will install bait boxes on your property. Please send the filled out form to isdonline@lynnma.gov. You can contact the Lynn Inspectional Services office at (781) 598-4000 with any questions.

https://www.lynnma.gov/cms/one.aspx?portalId=109810&pageId=136766

Construction Working Hours

Monday through Friday: 7 a.m. to 6 p.m.
(Saturday and Sunday work require local authorization)

Construction Progress Photos

(click on the photos to enlarge with descriptions)

January 2026 Drone Photos

Week of January 09, 2026

Transporting remaining soil stockpiles off-site is nearing completion.
Structural steel erection progress as of January 09, 2026 (near future front entrance).
Delivery of structural steel is ongoing.
Structural steel erection progress as of January 09, 2026 (facing southeast).
Structural steel erection progress as of January 09, 2026 (facing north).
Structural steel erection progress as of January 09, 2026 (facing south).

Week of January 02, 2026

Applying waterproofing to concrete foundation wall.
Structural steel erection is ongoing.
Structural steel erection progress (cont.)

Week of December 26, 2025

Crane assembly for structural steel erection.
Structural steel deliveries commenced.
Structural steel erection commenced.

Week of December 19, 2025

Crane delivery for steel erection.
Backfilling of structural fill.
Asphalt Binder placement in preparation for steel deliveries.

December 2025 Drone Photos

Week of December 12, 2025

Excavating for underground utilities and building foundation.
Installation of permanent stainless steel guardrails/handrails for Sission student playgroud access ramp is nearing completion.
Concrete pour for tall foundation walls.
Applying waterproofing to concrete foundation wall.
Grading crushed stone in preparation for asphalt binder placement.

Week of December 05, 2025

Concrete forms placed for the building foundation.
Exterior Masonry (Brick) Mockup.
Current progress of concrete foundations for new Pickering Middle School.
Installation of permanent stainless steel guardrails/handrails commenced for Sission student playgroud access ramp

Week of November 28, 2025

Laying gravel in preparation for asphalt binder placement for the future main parking lot, which will be utilized for structural steel deliveries.
Installation of concrete forms in preparation for concrete foundation pour is ongoing.
Delivery/Installation of a centralized, exterior grease trap.

Week of November 21, 2025

Transporting remaining soil stockpiles off-site is ongoing.
Delivery of a heater and fuel cell delivered to the site in preparation for pouring concrete (foundations) in cold temperatures.
Installation of temporary power conduit.
Installation of rebar for the northwest continuous footing is ongoing.

Week of November 14, 2025

Installation of foundation AVB (Self-Adhered Air and Vapor Barrier Membrane) is ongoing.
Steel Rebar delivered to site for foundations.
Placement of steel rebar in preparation for foundation concrete pour.

November 2025 Drone Photos

Week of November 07, 2025

Loading excavated soil stockpiles for transportation off-site.
Installation of forms and rebar for foundation footing concrete pour.
Installation of AVB (Self-Adhered Air and Vapor Barrier Membrane).
Forms removed from new foundation walls.

Week of October 31, 2025

The Jet grout working platform brought down to subgrade for the installation of the remaining Earthquake Drains and Rigged Inclusions.
Demobilization of Jet Grout drill equipment.
Progress of foundation walls - 10/31/25

Week of October 24, 2025

Excavating for the jet grout working platform in the northeast corner of the new Pickering School building footprint.
Site overview facing east (Jet Grouting and forming concrete foundation walls).
Concrete contractor's "lay-down" area as foundation work continues.

Week of October 17, 2025

Setting Concrete forms and rebar for eastern foundation wall.
Concrete wall forms ready for tall foundation wall concrete pour.
Installing of Jet Grout Columns is ongoing (left side) w/ concrete work (right side).

October 2025 Drone Photos

Week of October 10, 2025

Site overview (facing Northeast) - October 2025
Site overview (facing West) - October 2025
Site overview (facing Southwest) - October 2025

Week of October 03, 2025

Removal of temporary forms ("Stripped") around strip footings & foundation walls along east side of the new School.
Backfilling along footings/foundation walls along northside of the new School.

Construction Logistics Plan

Trucking/Delivery Route
Crane Locations for steel erection.
Loading Bay Zones

CURRENT PHASE                                

Early Structure - Janaury 2026

UPCOMING PHASES                                

Structure/Early Facade - Summer 2026
Project Complete - December 2027
Building Facade - Summer 2026 - January 2027
Hardscape - Summer 2027

COMPLETED PHASES

Early Enabling - Spring 2024
Enabling/Demo - Summer 2024
Foundations - Summer 2025 - December 2025