Pickering Middle School

Building Project

Construction Phase

ANNOUNCEMENTS

 

Increased Rodent activity around new Pickering Construction Site?

Construction activities can disturb rodents living in/below/around construction sites. Experiencing increased rodent activity around you house, please fill out the form using the link below. The City will install bait boxes on your property. Please send the filled out form to isdonline@lynnma.gov . You can contact the Lynn Inspectional Services office at (781) 598-4000 with any questions.

https://www.lynnma.gov/common/pages/GetFile.ashx?key=8AIEAAv9

Construction Working Hours

 

7AM – 6PM – Monday – Friday

(Saturday and Sunday work require local authorization)

Construction Progress Photos

(click on photo to enlarge with description)

 

Week of 09.27.24

Installing sewer pipe
Backfilling sewer manhole structure

Pickering Groundbreaking Ceremony

Project Team Members
Pickering Students with Local/State Officials
New Pickering School Groundbreaking Ceremony
Project Team Members with Local/State Officials
New Pickering School Groundbreaking Ceremony
New Pickering School Groundbreaking Ceremony with Construction Progress
Pickering School Building Committee Members with Local/State Officials
New Pickering School Groundbreaking Ceremony
New Pickering School Groundbreaking Ceremony with Construction Progress (Extended View)

Week of 09.20.24

Loading soil to haul off site from the yellow stockpile
Loading soil to haul off site from the yellow stockpile
Trucks on standby to remove yellow soil.

Week of 09.13.24

Completion of temp bridge (west)
Digging for green soil test samples
Digging and backfilling for green soil test samples

Week of 09.06.24

Infiltration system #4 installation
Second bridge for vehicle access across MWRA line
Temporary playground fenced in and turned over to Sisson school
Laying down asphalt and spraying hydroseed for temporary playground

Week of 08.30.24

Sisson School egress on top of retaining wall
Sewer Manhole installation
Infiltration system #4 installation
Retaining wall progress

Week of 08.23.24

Retaining Wall installation
Sisson school egress and overhead protection
Soil Stockpile in laydown area (blue soil)
Excavation for retaining wall and infiltration system

Week of 08.16.24

Contractor laydown area prepped with dense grade gravel.
Egress pathway along eastern wall of Sisson School prepped for asphalt and scaffolding
Sheet pile support of excavation completed
Safety Cables and stanchions installed on top of all sheet piles
Excavation along south side of Sisson School

Week of 08.08.24

Site Preparation for Retaining Wall at Sisson Play Area
Support of Excavation Completed for West Side of Building Excavation
Protection of Existing MWRA Easement and Creation of Site Entrance from Magnolia Ave
Temporary Crossing over MWRA Line for Site Logistics
Support of Excavation Complete for Sisson Play Area Retaining Wall